SIMEC Booster Pump Station

Overview

Aquest, a leading electrical contractor, successfully completed the comprehensive electrical, mechanical, and civil works for the SIMEC Booster Pump project. This project involved extensive modifications, installations, and
integrations essential for the efficient and safe operation of a new industrial facility. The project scope required meticulous planning, coordination, and execution across various engineering disciplines, ensuring compliance with stringent safety and quality standards.

Project

Iron Duke Booster Pump Station

Client

SIMEC Mining

What We Did

Comprehensive electrical installation

Project Scope

1. Modifying MCC-009:
• Installation of two new modules in tier R0 as per specifications.
• Modification of tier busbar droppers as per specifications.
• Installation of an 800 A breaker to supply power to the new switchboard 2-MCC-010.
2. Modifying Existing PLC 2-PCC-010:
• Making modifications as shown in the provided sketches and documents.
• Installation of a fibre breakout box, ETAP, I/O card, and associated cabling.
• Installation of a cable run between 2-PCC-010 and the existing phone box in 2-BS-009.
• Integration of the FIP (Field Interface Panel) to the existing SiPass system.
3. Running Cables to Switchroom 2-BS-010:
• Supplying, connecting, and running all cables to their termination points.
• Running power cables from breaker 2-MCC-010-Q1 to the new switchroom 2-BS-010 incomer.
• Running fibre cables from PLC 2-PCC-010 in switchroom 2-BS-009 to the new switchroom 2-BS-010.
• Completing fibre termination and testing for communication cables.
4. Installing Switchroom 2-BS-010:
• Assisting in the installation of the switchroom frames and fitment onto stubs.
• Dressing and terminating all cables running between switchroom 2-BS-009 and 2-BS-010.
• Installation of earthing as per specifications.
5. Running Power and Control to Pump Stations:
• Making electrical connections to the pumps and devices installed at the boost pump stations.
• Burying the cable between the two pump stations in a trench for safety and accessibility.
• Connecting and proving the earthing for the foundations of the pumps.
• Supplying and installing cable supports.

6. Installing Field Devices:
• Installing pressure indicator transmitters at specified locations on the tailing’s lines.
• Power-commissioning the installed devices.
7. Testing and Commissioning:
• Completing testing and commissioning of all installed equipment.
• Power commissioning all equipment.
8. Compliance with Electrical Standards and Regulations:
• Adhering to the requirements of the Electricity Act and Regulations.
• Following AS/NZS 3000 Wiring rules.
• Completing an Electrical Certificate of Compliance.
• Complying with all electrical safety protocols and procedures.